OSHA 1926.251 / ASME B30.9 — Slings
What it means on the job
Nylon slings in contact with sharp edges must have corner protectors (softeners) to prevent the sling from being cut under load. A sling failure under a 2,000 lb load is a fatal hazard. OSHA and ASME B30.9 require edge protection whenever a sling contacts a sharp radius.
Tested in 1 CraftIQ puzzle
- whats-wrongUnion Hall Training: Rigging and Hoisting
Related OTHER sections
OSHA 1910.212 / SMACNA Safety Manual
Pittsburgh lock seam machines have pinch points that can amputate fingers. Machine guards are required by OSHA and must never be bypassed or removed. SMACNA apprenticeship training specifically emphasizes: never defeat a machine guard.
OSHA 1910.252 / AWS Z49.1
Plasma cutting produces intense UV/IR radiation and bright arc flash that causes eye damage (arc eye) and skin burns. A welding screen or curtain must be deployed around the cutting area to protect the operator and nearby workers.
OSHA 1910.252(c) / ACGIH TLV Guidelines
OSHA 1910.252(c) requires adequate ventilation for all welding operations. In confined or enclosed spaces, mechanical ventilation must provide a minimum of 2,000 CFM per welder. Welding fumes contain hexavalent chromium, manganese, and other toxic metals that exceed OSHA PELs without proper exhaust ventilation.
OSHA 1926.753 / ASME B30.5
Suspended loads must have a tag line to allow workers to guide the load without placing hands on it. Without a tag line, workers must physically push/pull the suspended load, putting them in the fall zone — a leading cause of rigging fatalities.
OSHA 29 CFR 1910.104(b)(3)(iii) / NFPA 55 bulk-oxygen siting table (referenced by NFPA 99 ch. 5)
This installation fails. Bulk oxygen siting per OSHA 29 CFR 1910.104(b)(3)(iii) and the NFPA 55 bulk-oxygen siting table (the basis NFPA 99 ch. 5 references) requires the storage to be at least 50 feet from combustible structures. The scenario places it only 15 feet from a combustible structure — far short of the 50-foot minimum — so the install is non-compliant and unsafe. The 25-foot clearance often quoted to combustible structures applies only where the structure has fire-resistive exterior walls or is sprinklered, and the 10-foot figure applies only to openings in fire-resistive walls; neither condition is stated here. Air-intake separation is likewise typically larger than the 20 feet the puzzle implied. The non-combustible roof, security fence, and DOT signage are fine, but the combustible-structure clearance is the controlling failure.
Plate-and-frame manufacturer gasket maintenance specifications / AHRI Standard 400 — Liquid to Liquid Heat Exchangers (TEMA covers shell-and-tube only)
Deteriorating gaskets allow cross-contamination between the two fluid circuits and external leaks. Gaskets degrade from excessive temperature, chemical exposure, or age. The heat exchanger must be disassembled and all gaskets replaced per manufacturer specifications. Running with leaking gaskets risks contaminating the clean circuit.